Let’s solve the question shown in the image.
—
Given:
A can complete the job in 21 days → A’s 1 day work =
B can complete the job in 14 days → B’s 1 day work =
A works alone for 6 days.
Then A and B work together to complete the job.
We need to find how many days the work lasted in total.
—
Step 1: Work done by A in 6 days
A’s 1 day work =
In 6 days, A does:
6 \times \frac{1}{21} = \frac{6}{21} = \frac{2}{7}
So, work remaining =
—
Step 2: A and B working together
A’s 1 day work =
B’s 1 day work =
Together in 1 day they do:
\frac{1}{21} + \frac{1}{14} = \frac{2 + 3}{42} = \frac{5}{42}
Let the number of days A and B worked together be
Then,
x \times \frac{5}{42} = \frac{5}{7}
Solve for :
x = \frac{5}{7} \div \frac{5}{42} = \frac{5}{7} \times \frac{42}{5} = 6
—
Step 3: Total duration of work
A worked 6 days alone
Then A and B worked together for 6 more days
Total = 6 + 6 = 12 days
—
✅ Final Answer: 12 days
But note: this is not listed as an option. Options given are:
A) 5
B) 8
C) 7
D) 6
Looks like the question is asking “How many days did the work last in total?”, which is 12, but perhaps it meant:
How many more days did they work together after the first 6 days?
In that case, the number of days A and B worked together is 6, so:
✅ Correct Option: D) 6